Question 8
A client from the banking industry operates its IBM Z environment in two data centers with a database of 10 kilometers (6.2 miles). Each data center has one IBM z14 and one DS8K storage system, which are PPRC enabled.
Due to regulations, this client has the need to implement a near-continuous availability solution including long-distance disaster recovery for a new-to-build third site with a new third storage system.
Which of the following solutions satisfies the requirements?
GDPS Metro HyperSwap Manager
Correct answer: B
Explanation:
Reference: https://www.ibm.com/developerworks/community/blogs/accelerate/resource/GDPS_Update_100317.pdf?lang=en (16)
Reference: https://www.ibm.com/developerworks/community/blogs/accelerate/resource/GDPS_Update_100317.pdf?lang=en (16)