Demo Questions

Question 1

You are the project manager of the NHQ project for your company. You are working with your project team to complete a risk audit. A recent issue that your project team responded to, and management approved, was to increase the project schedule because there was risk surrounding the installation time of a new material. Your logic was that with the expanded schedule there would be time to complete the installation without affecting downstream project activities. What type of risk response is being audited in this scenario?


  1. Avoidance
  2. Mitigation
  3. Parkinson's Law
  4. Lag Time
Correct answer: A



Question 2

You are the project manager for your organization. You are preparing for the quantitative risk analysis. Mark, a project team member, wants to know why you need to do quantitative risk analysis when you just completed qualitative risk analysis. Which one of the following statements best defines what quantitative risk analysis is?


  1. Quantitative risk analysis is the process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.
  2. Quantitative risk analysis is the planning and quantification of risk responses based on probability and impact of each risk event.
  3. Quantitative risk analysis is the review of the risk events with the high probability and the highest impact on the project objectives.
  4. Quantitative risk analysis is the process of numerically analyzing the effect of identified risks on overall project objectives.
Correct answer: D



Question 3

Which of the following is NOT a sub-process of Service Portfolio Management?


  1. Service Portfolio Update
  2. Business Planning Data
  3. Strategic Planning
  4. Strategic Service Assessment
  5. Service Strategy Definition
Correct answer: B