Download ISACA.CRISC.ActualTests.2024-07-17.871q.tqb

Download Exam

File Info

Exam Certified in Risk and Information Systems Control
Number CRISC
File Name ISACA.CRISC.ActualTests.2024-07-17.871q.tqb
Size 3 MB
Posted Jul 17, 2024
Download ISACA.CRISC.ActualTests.2024-07-17.871q.tqb

How to open VCEX & EXAM Files?

Files with VCEX & EXAM extensions can be opened by ProfExam Simulator.

Purchase

Coupon: MASTEREXAM
With discount: 20%






Demo Questions

Question 1

Which of the following is the MOST important reason to maintain key risk indicators (KRIs)?


  1. In order to avoid risk
  2. Complex metrics require fine-tuning
  3. Risk reports need to be timely
  4. Threats and vulnerabilities change over time
Correct answer: D
Explanation:
Threats and vulnerabilities change over time and KRI maintenance ensures that KRIs continue to effectively capture these changes.The risk environment is highly dynamic as the enterprise's internal and external environments are constantly changing. Therefore, the set of KRIs needs to be changed over time, so that they can capture the changes in threat and vulnerability.
Threats and vulnerabilities change over time and KRI maintenance ensures that KRIs continue to effectively capture these changes.
The risk environment is highly dynamic as the enterprise's internal and external environments are constantly changing. Therefore, the set of KRIs needs to be changed over time, so that they can capture the changes in threat and vulnerability.



Question 2

You are the project manager of a HGT project that has recently finished the final compilation process. The project customer has signed off on the project completion and you have to do few administrative closure activities. In the project, there were several large risks that could have wrecked the project but you and your project team found some new methods to resolve the risks without affecting the project costs or project completion date. What should you do with the risk responses that you have identified during the project's monitoring and controlling process?


  1. Include the responses in the project management plan.
  2. Include the risk responses in the risk management plan.
  3. Include the risk responses in the organization's lessons learned database.
  4. Nothing. The risk responses are included in the project's risk register already.
Correct answer: C
Explanation:
The risk responses that do not exist up till then, should be included in the organization's lessons learned database so other project managers can use these responses in their project if relevant.
The risk responses that do not exist up till then, should be included in the organization's lessons learned database so other project managers can use these responses in their project if relevant.



Question 3

You are the project manager of GHT project. You have identified a risk event on your project that could save $100,000 in project costs if it occurs. Which of the following statements BEST describes this risk event?


  1. This risk event should be mitigated to take advantage of the savings.
  2. This is a risk event that should be accepted because the rewards outweigh the threat to theproject.
  3. This risk event should be avoided to take full advantage of the potential savings.
  4. This risk event is an opportunity to the project and should be exploited.
Correct answer: D
Explanation:
This risk event has the potential to save money on project costs, so it is an opportunity, and the appropriate strategy to use in this case is the exploit strategy. The exploit response is one of the strategies to negate risks or threats appear in a project. This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized.Exploiting a risk event provides opportunities for positive impact on a project. Assigning more talented resources to the project to reduce the time to completion is an example of exploit response.
This risk event has the potential to save money on project costs, so it is an opportunity, and the appropriate strategy to use in this case is the exploit strategy. The exploit response is one of the strategies to negate risks or threats appear in a project. This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized.
Exploiting a risk event provides opportunities for positive impact on a project. Assigning more talented resources to the project to reduce the time to completion is an example of exploit response.









CONNECT US

Facebook

Twitter

PROFEXAM WITH A 20% DISCOUNT

You can buy ProfExam with a 20% discount!



HOW TO OPEN VCEX FILES

Use ProfExam Simulator to open VCEX files