Question 2
Scenario 1 "Medical Domain"
You are working as a test manager in the medical domain leading a team of system testers. You are currently working on a major release of the product which gives customers many new features and resolves a number of problem reports from previous releases.
Explain how the above mentioned report may differ from a report that you produce for the project manager, who is a test specialist Select TWO items from the following options that can be used to report to the project manager and would not be included in a report to senior management.
Show details on effort spent
List of all outstanding defects with their priority and severity
State recommendations for release
Correct answer: AB