Question 3
You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days, week, or months. How should you achieve the goal without scheduling the same requirements multiple times manually by using the schedule board (or with the schedule assistant)?
Use Multi-Resource Scheduling
Use Resource Crew Scheduling
Use Universal Resource Scheduling
Correct answer: B
Explanation:
https://docs.microsoft.com/en-us/dynamics365/customer-engagement/field-service/multi-resource-scheduling-requirement-groups
https://docs.microsoft.com/en-us/dynamics365/customer-engagement/field-service/multi-resource-scheduling-requirement-groups