Question 5
Refer to the exhibit.
An administrator has been informed that a new workload will be deployed in six months with these characteristics.
CPU: 210 GHz
Memory: 600 GiB
Storage:11.72 TiB
Upon receiving the new project notification, the administrator creates a scenario to determine whether or not the Nutanix cluster has enough space capacity to properly handle the new workload.
Why is the Overall Cluster runway showing that cluster resources are not exhausted (red color)?
Target analysis timeframe starts after additional resources are added.
There are enough available resources to support the new workload.
Additional resources will be added before the new workload is added
Target analysis timeframe ends before the new workload is added.
Correct answer: D
Explanation:
https://support-portal.nutanix.com/page/documents/details?targetId=Prism-CentralGuide-Prismv5_19:mul-resource-planning-runway-view-pc-r.html
https://support-portal.nutanix.com/page/documents/details?targetId=Prism-CentralGuide-Prismv5_19:mul-resource-planning-runway-view-pc-r.html