Question 3
Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)
Override rate > Job rate schedule > Resource class rate schedule > Person rate schedule
Person rate schedule > Job rate schedule > Resource class rate schedule > Override rate
Job rate schedule > Resource class rate schedule > Override rate > Person rate schedule
Override rate > Person rate schedule > Job rate schedule > Resource class rate schedule
Resource class rate schedule > Override rate > Job rate schedule > Person rate schedule
Correct answer: D
Explanation:
Reference https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_8718794B26A7BB93E040D30A688149A3