Question 1
Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a 10 spread point scale resembles: 0-4-10-11-14-13-10-4-0-0.
Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two.)
Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to a project template.
Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to the resource class.
Use the predefined Bell Curve spread with small deviations on the spread points.
Use the predefined S-Curve spread with small deviations on the spread points.
Correct answer: BC