Question 1

Which document defines how a project is executed, monitored and controlled, and closed?


  1. Strategic plan
  2. Project charter
  3. Project management plan
  4. Service level agreement
Correct answer: C
Explanation:
4.2.3.1 Project Management Plan The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes. Project baselines include, but are not limited to:Scope baseline (Section 5.4.3.1), Schedule baseline (Section 6.6.3.1), and Cost baseline (Section 7.3.3.1). Subsidiary plans include, but are not limited to:Scope management plan (Section 5.1.3.1), Requirements management plan (Section 5.1.3.2), Schedule management plan (Section 6.1.3.1), Cost management plan (Section 7.1.3.1), Quality management plan (Section 8.1.3.1), Process improvement plan (Section 8.1.3.2), Human resource management plan (Section 9.1.3.1), Communications management plan (Section 10.1.3.1), Risk management plan (Section 11.1.3.1), Procurement management plan (Section 12.1.3.1), and Stakeholder management plan (Section 13.2.3.1). Among other things, the project management plan may also include the following:Life cycle selected for the project and the processes that will be applied to each phase; Details of the tailoring decisions specified by the project management team as follows:Project management processes selected by the project management team, Level of implementation for each selected process, Descriptions of the tools and techniques to be used for accomplishing those processes, and Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs. Description of how work will be executed to accomplish the project objectives; Change management plan that documents how changes will be monitored and controlled; Configuration management plan that documents how Configuration management will be performed; Description of how the integrity of the project baselines will be maintained; Requirements and techniques for communication among stakeholders; and Key management reviews for content, the extent of, and timing to address, open issues and pending decisions. The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.
4.2.3.1 Project Management Plan 
The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes. 
Project baselines include, but are not limited to:
  • Scope baseline (Section 5.4.3.1), 
  • Schedule baseline (Section 6.6.3.1), and 
  • Cost baseline (Section 7.3.3.1). 
Subsidiary plans include, but are not limited to:
  • Scope management plan (Section 5.1.3.1), 
  • Requirements management plan (Section 5.1.3.2), 
  • Schedule management plan (Section 6.1.3.1), 
  • Cost management plan (Section 7.1.3.1), 
  • Quality management plan (Section 8.1.3.1), 
  • Process improvement plan (Section 8.1.3.2), 
  • Human resource management plan (Section 9.1.3.1), 
  • Communications management plan (Section 10.1.3.1), 
  • Risk management plan (Section 11.1.3.1), 
  • Procurement management plan (Section 12.1.3.1), and 
  • Stakeholder management plan (Section 13.2.3.1). 
Among other things, the project management plan may also include the following:
  • Life cycle selected for the project and the processes that will be applied to each phase; 
  • Details of the tailoring decisions specified by the project management team as follows:
    • Project management processes selected by the project management team, 
    • Level of implementation for each selected process, 
    • Descriptions of the tools and techniques to be used for accomplishing those processes, and 
    • Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs. 
  • Description of how work will be executed to accomplish the project objectives; 
  • Change management plan that documents how changes will be monitored and controlled; 
  • Configuration management plan that documents how Configuration management will be performed; 
  • Description of how the integrity of the project baselines will be maintained; 
  • Requirements and techniques for communication among stakeholders; and 
  • Key management reviews for content, the extent of, and timing to address, open issues and pending decisions. 
The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.



Question 2

An input used in developing the communications management plan is:


  1. Communication models.
  2. Enterprise environmental factors.
  3. Organizational communications.
  4. Organizational cultures and styles.
Correct answer: B
Explanation:
10.1.3.1 Communications Management Plan The communications management plan is a component of the project management plan that describes how project communications will be planned, structured, monitored, and controlled. The plan contains the following information:Stakeholder communication requirements; Information to be communicated, including language, format, content, and level of detail; Reason for the distribution of that information; Time frame and frequency for the distribution of required information and receipt of acknowledgment or response, if applicable; Person responsible for communicating the information; Person responsible for authorizing release of confidential information; Person or groups who will receive the information; Methods or technologies used to convey the information, such as memos, e-mail, and/or press releases; Resources allocated for communication activities, including time and budget; Escalation process identifying time frames and the management chain (names) for escalation of issues that cannot be resolved at a lower staff level; Method for updating and refining the communications management plan as the project progresses and develops; Glossary of common terminology; Flow charts of the information flow in the project, workflows with possible sequence of authorization, list of reports, and meeting plans, etc.; and Communication constraints usually derived from a specific legislation or regulation, technology, and organizational policies, etc. The communications management plan can also include guidelines and templates for project status meetings, project team meetings, e-meetings, and e-mail messages. The use of a project website and project management software can also be included if these are to be used in the project.
10.1.3.1 Communications Management Plan 
The communications management plan is a component of the project management plan that describes how project communications will be planned, structured, monitored, and controlled. The plan contains the following information:
  • Stakeholder communication requirements; 
  • Information to be communicated, including language, format, content, and level of detail; 
  • Reason for the distribution of that information; 
  • Time frame and frequency for the distribution of required information and receipt of acknowledgment or response, if applicable; 
  • Person responsible for communicating the information; 
  • Person responsible for authorizing release of confidential information; 
  • Person or groups who will receive the information; 
  • Methods or technologies used to convey the information, such as memos, e-mail, and/or press releases; 
  • Resources allocated for communication activities, including time and budget; 
  • Escalation process identifying time frames and the management chain (names) for escalation of issues that cannot be resolved at a lower staff level; 
  • Method for updating and refining the communications management plan as the project progresses and develops; 
  • Glossary of common terminology; 
  • Flow charts of the information flow in the project, workflows with possible sequence of authorization, list of reports, and meeting plans, etc.; and 
  • Communication constraints usually derived from a specific legislation or regulation, technology, and organizational policies, etc. 
The communications management plan can also include guidelines and templates for project status meetings, project team meetings, e-meetings, and e-mail messages. The use of a project website and project management software can also be included if these are to be used in the project.



Question 3

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?


  1. Identify Risks
  2. Control Risks
  3. Plan Risk Management
  4. Plan Risk Responses
Correct answer: D
Explanation:
Process: 11.5 Plan Risk ResponsesDefinition: The process of developing options and actions to enhance opportunities and to reduce threats to project objectives.Key Benefit: The key benefit of this process is that it addresses the risks by their priority, inserting resources and activities into the budget, schedule and project management plan as needed.Inputs 1.Risk management plan 2.Risk register   Tools & Techniques 1.Strategies for negative risks or threats 2.Strategies for positive risks or opportunities 3.Contingent response strategies 4.Expert judgment   Outputs 1.Project management plan updates 2.Project documents updates
Process: 11.5 Plan Risk Responses
Definition: The process of developing options and actions to enhance opportunities and to reduce threats to project objectives.
Key Benefit: The key benefit of this process is that it addresses the risks by their priority, inserting resources and activities into the budget, schedule and project management plan as needed.
Inputs 
1.Risk management plan 
2.Risk register 
  
Tools & Techniques 
1.Strategies for negative risks or threats 
2.Strategies for positive risks or opportunities 
3.Contingent response strategies 
4.Expert judgment 
  
Outputs 
1.Project management plan updates 
2.Project documents updates