Download PMI.PMP.Pass4Sure.2018-03-08.910q.vcex

Download Exam

File Info

Exam Project Management Professional
Number PMP
File Name PMI.PMP.Pass4Sure.2018-03-08.910q.vcex
Size 2 MB
Posted Mar 08, 2018
Download PMI.PMP.Pass4Sure.2018-03-08.910q.vcex

How to open VCEX & EXAM Files?

Files with VCEX & EXAM extensions can be opened by ProfExam Simulator.

Purchase

Coupon: MASTEREXAM
With discount: 20%






Demo Questions

Question 1

In Project Cost Management, which input is exclusive to the Determine Budget process?


  1. Scope baseline
  2. Organizational process assets
  3. Project schedule
  4. Resource calendars
Correct answer: D



Question 2

The key benefit of the Monitoring and Controlling Process Group is the ability to:


  1. establish and manage project communication channels, both external and internal to the project team.
  2. influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.
  3. monitor the ongoing project team against the team performance assessments and the project performance baseline.
  4. observe and measure project performance regularly and consistently to identify variances from the project management plan.
Correct answer: D



Question 3

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?


  1. Project Plan
  2. Responsibility Matrix
  3. Issue Log
  4. Scope Document
Correct answer: C



Question 4

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?


  1. Project sponsor
  2. Project manager
  3. Person responsible for project scheduling
  4. Person who is most familiar with the task
Correct answer: D



Question 5

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?


  1. Perform Quality Control
  2. Perform Quality Assurance
  3. Plan Quality
  4. Report Performance
Correct answer: A



Question 6

A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?


  1. Three weeks
  2. Four weeks
  3. Five weeks
  4. Six weeks
Correct answer: C



Question 7

What is the primary benefit of meeting quality requirements? 


  1. Quality metrics
  2. Less rework
  3. Quality control measurements
  4. Benchmarking
Correct answer: B
Explanation:



Question 8

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?


  1. Performance organizations
  2. Schedule baselines
  3. Work performance measurements
  4. Change requests
Correct answer: C



Question 9

Testing falls into which of the following categories of cost of quality?


  1. Internal failure costs
  2. Prevention costs
  3. Appraisal costs
  4. External failure costs
Correct answer: C



Question 10

Which of the following events would result in a baseline update?


  1. A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion. 
  2. A customer has approved a change request broadening the project scope and increasing the budget.
  3. One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
  4. One of the key project team resources has left the team and no replacement is available.
Correct answer: B









CONNECT US

Facebook

Twitter

PROFEXAM WITH A 20% DISCOUNT

You can buy ProfExam with a 20% discount!



HOW TO OPEN VCEX FILES

Use ProfExam Simulator to open VCEX files