Question 1

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?


  1. Historical relationships
  2. Dependency determination
  3. Bottom-up estimating
  4. Rolling wave planning
Correct answer: D



Question 2

An output of the Create WBS process is:


  1. Scope baseline.
  2. Change requests.
  3. Accepted deliverables.
  4. Variance analysis.
Correct answer: A



Question 3

A tool or technique used in the Control Procurements process is:


  1. Expert judgment.
  2. Performance reporting.
  3. Bidder conferences.
  4. Reserve analysis.
Correct answer: B



Question 4

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?


  1. Supportive
  2. Directive
  3. Controlling
  4. Instructive
Correct answer: A



Question 5

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?


  1. Project document updates
  2. Activity list
  3. Activity attributes
  4. Project calendars
Correct answer: C



Question 6

An input to the Identify Stakeholders process is:


  1. The project management plan.
  2. The stakeholder register.
  3. Procurement documents.
  4. Stakeholder analysis.
Correct answer: C



Question 7

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?


  1. $50
  2. $100
  3. $125
  4. $200
Correct answer: D
Explanation:
EAC=BAC/CPI and CPI=EV/AC CPI = EV/ AC = 25/50 = 0.5 EAC = BAC/ CPI = 100/0.5 = $200
EAC=BAC/CPI and CPI=EV/AC 
CPI = EV/ AC = 25/50 = 0.5 
EAC = BAC/ CPI = 100/0.5 = $200



Question 8

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?


  1. Influencing
  2. Motivation
  3. Negotiation
  4. Trust building
Correct answer: B



Question 9

A project manager should communicate to stakeholders about resolved project issues by updating the:


  1. project records
  2. project reports
  3. stakeholder notifications
  4. stakeholder register
Correct answer: C



Question 10

A disadvantage associated with virtual teams is that they:


  1. Require communication technology that is not readily available.
  2. Create difficulties when including people with disabilities.
  3. Often cannot accommodate teams that work different hours or shifts.
  4. Create the possibility for misunderstandings to arise.
Correct answer: D