Demo Questions

Question 1

In which Project Management Process Group is the project charter developed?


  1. Monitoring and Controlling
  2. Executing
  3. Initiating
  4. Planning
Correct answer: C



Question 2

Monte Carlo is which type of risk analysis technique?


  1. Probability
  2. Quantitative
  3. Qualitative
  4. Sensitivity
Correct answer: B



Question 3

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?


  1. Authority
  2. Role
  3. Competency
  4. Responsibility
Correct answer: C



Question 4

Which of the following reduces the probability of potential consequences of project risk events?


  1. Preventive action
  2. Risk management
  3. Corrective action
  4. Defect repair
Correct answer: A



Question 5

Which of the following is the primary output of the Identify Risks process?


  1. Risk management plan
  2. Risk register
  3. Change requests
  4. Risk response plan
Correct answer: B



Question 6

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?


  1. Requirements traceability matrix
  2. Work breakdown structure (WBS) dictionary
  3. Requirements management plan
  4. Requirements documentation
Correct answer: A



Question 7

Which type of risk diagram is useful for showing time ordering of events?


  1. Ishikawa
  2. Milestone
  3. Influence
  4. Decision tree
Correct answer: C



Question 8

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?


  1. Program Management Body of Knowledge Guide
  2. The Standard for Program Management
  3. Organizational Project Management Maturity Model (OPM3$)
  4. Guide to the Project Management Body of Knowledge (PMBOKĀ®)
Correct answer: D



Question 9

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?


  1. Exploit
  2. Share
  3. Enhance
  4. Transfer
Correct answer: D



Question 10

Which of the following correctly explains the term "progressive elaboration'?


  1. Changing project specifications continuously
  2. Elaborate tracking of the project progress
  3. Elaborate tracking of the project specifications with a change control system
  4. Project specifications becoming more explicit and detailed as the project progresses
Correct answer: D