Demo Questions

Question 1

What takes place during the Closing a Project process?


  1. The post-project benefits reviews are performed
  2. Ownership of the project's products is transferred to the customer
  3. An End Stage Report is prepared for the final stage
  4. The project closure notification is reviewed and approved
Correct answer: B



Question 2

Which is an objective of the Closing a Project process? 


  1. Prepare the plan for the next stage
  2. Assess any benefits that have already been realized
  3. Produce a Benefits Review Plan to identify what benefits are expected
  4. Check that all benefits are realized before closing a project
Correct answer: B



Question 3

Which is a purpose of the Closing a Project process?


  1. Authorize the final stage of the project
  2. Confirm that all benefits defined in the Business Case have been achieved
  3. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
  4. Delegate day-to-day management of the end of the project to the Project Manager
Correct answer: C



Question 4

Which is an objective of the Closing a Project process?


  1. Review and approve the plan for project closure
  2. Review the performance of the project against its baseline
  3. Perform any post-project reviews
  4. Create a Benefits Review Plan
Correct answer: B



Question 5

Which is a purpose of the Controlling a Stage process?


  1. Produce a Team Plan for the work to be assigned to a Team Manager
  2. Select and implement actions that will resolve deviations from a plan within tolerance
  3. Obtain approvals for products delivered in a Work Package
  4. Update a Project Plan to incorporate the actuals from a Stage Plan
Correct answer: B



Question 6

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?


  1. Directing a Project
  2. Managing a Stage Boundary
  3. Controlling a Stage
  4. Starting up a Project
Correct answer: C



Question 7

Which process is triggered towards the end of the final stage when all the assigned work has been completed?


  1. Managing a Stage Boundary
  2. Managing Product Delivery
  3. Closing a Project
  4. Controlling a Stage
Correct answer: C



Question 8

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances? 


  1. Directing a Project
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Managing Product Delivery
Correct answer: B



Question 9

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?


  1. Product Description
  2. Team Plan
  3. Work Package
  4. Stage Plan
Correct answer: C



Question 10

Which is a purpose of the Directing a Project process? 


  1. Create and authorize the project mandate
  2. Ensure that work on products allocated to the team is authorized and agreed 
  3. Control the day-to-day running of the project
  4. Delegate day-to-day management of the project to the Project Manager
Correct answer: D