Question 1

Which product records any project outcomes perceived as negative by stakeholders?


  1. Business Case
  2. Project Plan
  3. Communication Management Strategy
  4. Project Product Description
Correct answer: A



Question 2

Which is NOT a purpose of a Benefits Review Plan?


  1. Define the period over which the cost-benefit analysis will be based
  2. Describe how to measure the performance of the project's products in operational use
  3. Define the scope, timing and ownership of the benefit reviews required
  4. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Correct answer: A



Question 3

Which product documents the information needed to demonstrate continued business justification?


  1. Business Case
  2. Communication Management Strategy
  3. Project Product Description
  4. Quality Management Strategy
Correct answer: A



Question 4

What is an off-specification?


  1. A new requirement
  2. A quality tolerance
  3. A type of issue
  4. A major risk
Correct answer: C



Question 5

Which is a type of issue?


  1. A lesson
  2. A request for change
  3. An Exception Report
  4. A risk with an estimated high impact
Correct answer: B



Question 6

Which should be funded by a change budget?


  1. Increase in agreed scope
  2. Initiation stage
  3. Change Authority
  4. Handover activities
Correct answer: A



Question 7

Which should be funded from a change budget?


  1. The Starting up a Project process
  2. A fallback plan
  3. An agreed change to the scope of a project
  4. A change to a plan, within allocated tolerances, due to poor estimating
Correct answer: C



Question 8

Which is the Issue Register NOT used for?


  1. Capture external events that are impacting a stage
  2. Record information about a deviation in stage tolerance
  3. Capture any threats or opportunities that might have an impact on a stage
  4. Record any problems identified when authorizing a Work Package
Correct answer: C



Question 9

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?


  1. Checkpoint Report
  2. Highlight Report
  3. Issue Report
  4. Product Status Account
Correct answer: C



Question 10

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?


  1. Raise a request for change
  2. Raise an off-specification
  3. Write an Exception Report
  4. Amend the Work Package
Correct answer: B