Download PRINCE2.PRINCE2-Foundation.SelfTestEngine.2019-08-22.171q.vcex

Download Exam

File Info

Exam PRINCE2 Foundation
Number PRINCE2-Foundation
File Name PRINCE2.PRINCE2-Foundation.SelfTestEngine.2019-08-22.171q.vcex
Size 104 KB
Posted Aug 22, 2019
Download PRINCE2.PRINCE2-Foundation.SelfTestEngine.2019-08-22.171q.vcex

How to open VCEX & EXAM Files?

Files with VCEX & EXAM extensions can be opened by ProfExam Simulator.

Purchase

Coupon: MASTEREXAM
With discount: 20%






Demo Questions

Question 1

Which should be funded by a change budget?


  1. Increase in agreed scope
  2. Initiation stage
  3. Change Authority
  4. Handover activities
Correct answer: A



Question 2

Which should be funded from a change budget?


  1. The Starting up a Project process
  2. A fallback plan
  3. An agreed change to the scope of a project
  4. A change to a plan, within allocated tolerances, due to poor estimating
Correct answer: C



Question 3

Which is the Issue Register NOT used for?


  1. Capture external events that are impacting a stage
  2. Record information about a deviation in stage tolerance
  3. Capture any threats or opportunities that might have an impact on a stage
  4. Record any problems identified when authorizing a Work Package
Correct answer: C



Question 4

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?


  1. Checkpoint Report
  2. Highlight Report
  3. Issue Report
  4. Product Status Account
Correct answer: C



Question 5

Which is the purpose of the Change theme?


  1. Prevent change to baselined products
  2. Identify, assess and control any potential and approved changes to baselined products
  3. Establish mechanisms to monitor and compare actual achievements against those planned
  4. Assess and control uncertainty
Correct answer: B



Question 6

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?


  1. Capture
  2. Examine
  3. Propose
  4. Decide
Correct answer: C



Question 7

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?


  1. Raise a request for change
  2. Raise an off-specification
  3. Write an Exception Report
  4. Amend the Work Package
Correct answer: B



Question 8

Which is a purpose of the Directing a Project process?


  1. Provide the information required to confirm if it is worthwhile to initiate a project
  2. Enable overall control of a project to be exercised by the Project Board
  3. Establish the level of control required by the Project Board after initiation.
  4. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
Correct answer: B



Question 9

Which is an objective of the Directing a Project process?


  1. Create and authorize the project mandate
  2. Provide management control and direction
  3. Control the day-to-day running of the project
  4. Provide accurate progress information to the Project Manager
Correct answer: B



Question 10

In what process is the authorization to deliver the project's products given?


  1. Starting up a Project
  2. Initiating a Project
  3. Managing a Stage Boundary
  4. Directing a Project
Correct answer: D