Question 10
Comparing the SAP Activate methodology with Waterfall, what activities are performed by the new project roles?
Product owner to discuss schedule with the customer
Scrum master to prepare the project plan
Scrum master and project sponsor to define the project charter
Scrum team to review best practices
Correct answer: D
Explanation:
In Agile methodologies like SAP Activate, Scrum teams are responsible for reviewing and applying best practices to ensure effective solution implementation. Unlike Waterfall, where project managers control most activities, Agile teams are self-organized and collaborate on continuous improvement.