Download Scrum.PSM II.CertDumps.2024-05-15.100q.tqb

Download Exam

File Info

Exam Professional Scrum Master II
Number PSM II
File Name Scrum.PSM II.CertDumps.2024-05-15.100q.tqb
Size 368 KB
Posted May 15, 2024
Download Scrum.PSM II.CertDumps.2024-05-15.100q.tqb


How to open VCEX & EXAM Files?

Files with VCEX & EXAM extensions can be opened by ProfExam Simulator.

Purchase

Coupon: MASTEREXAM
With discount: 20%






Demo Questions

Question 1

A Scrum Master is not only a servant-leader to the Scrum Team and organization, it's also considered a management position.Which three activities describe what a Scrum Master manages as reflected by the Scrum Guide? (Choose three.)


  1. Reporting on the performance of the Sprint.
  2. The way Scrum is understood and enacted within the organization.
  3. Managing the capacity and utilization of each Development Team member.
  4. Managing the process in which Scrum is applied.
  5. Managing the Product Backlog items and work in the Sprint Backlog.
  6. Removing organizational impediments that limits the team's progress and productivity.
Correct answer: BDF



Question 2

An organization has just hired you as a new Scrum Master to help them transition their teams from their current traditional process to Scrum. The teams are currently structured to specialize in a single function. This is also known as component teams where a team would only address a single layer (i.e. design, frontend, backend, database, testing, etc.). You've introduced the concept of cross-functional teams where all the skills needed to produce business functionality, from end to end, are inside of a single team.What should you keep in mind when transitioning from siloed teams to cross-functional teams? (Choose two.)


  1. It is easier to compare the performance between cross-functional teams in order to identify to which teams to assign tasks and which teams need additional coaching.
  2. Newly formed teams will need time to stabilize before reaching their peak performance. During the initial stages of forming, performance will suffer and productivity may be low, although even then delivery of business value is still likely to increase.
  3. Without feature teams, you cannot do Scrum. Postpone Scrum adoption until the teams are reorganized in feature teams.
  4. People from the different layers and components will need time to become accustomed to working and delivering unified functionality together as one Scrum Team thus productivity may suffer.
Correct answer: BD



Question 3

Paul is a Product Owner for multiple products. Each product is allocated a dedicated Scrum Team and a set budget. Based on the average velocity of a previous product release, Paul had estimated a new product to take 9 Sprints to complete. The average velocity of the previous product release was 50 completed units of work per Sprint. Over the first 3 Sprints, the Development Team reported an average velocity of 40 completed units per Sprint, while not fully completing the required integration tests. The Development Team estimates that integration testing would require additional effort to make the increments shippable. TheDevelopment Team is unsure if the required velocity is achievable.What is the most effective way to recover?
 


  1. In the next Sprints, the Development Team strives to make the selected work as close to 'done' as possible and at the minimum 90% completed. Any undone work is divided into new Product Backlog Items that will be deferred to the last Sprint in order to maintain stable velocity.
  2. The Development Team informs Paul that the progress he has perceived to date is not correct. The Increment is not releasable. They give Paul their estimate of the effort it would take to get the previous work 'done', and suggest doing that work first before proceeding with new features. The team also re-estimates the effort to make the remaining Product Backlog items 'done', including all integration effort. In the end, it is Paul's call to continue the project or to cancel.
  3. The Scrum Master will manage the Sprint Backlog and assign work to the Development Team members to ensure maximum utilization of each member. He/ she will keep track of unused resources so that it does not impact the budget. Unused budget can be allocated for additional Sprints if needed.
  4. The Scrum Master sets the open work aside to be performed in one or more release Sprints. They remind Paul to find funding for enough Release Sprints in which this remaining work can be done. Up to one release Sprint per three development Sprints may be required. It is Paul's role to inform users and stakeholders of the impact on the release date.
Correct answer: B









PROFEXAM WITH A 20% DISCOUNT

You can buy ProfExam with a 20% discount!



HOW TO OPEN VCEX FILES

Use ProfExam Simulator to open VCEX files